USS Gary Works – 3
Location: Gary, Indiana
No. 8 Blast furnace repairs
This project was successfully completed as a $42 million contract with more than 230,000 direct hire hours and 450 peak manpower.
The scope included fixed fee/reimbursable commercial agreement and a first skip incline replacement.
$42MM
Contract price
230K
Direct hire hours
450
Peak manpower
Scope of Work
- Blast furnace repairs
- Fixed fee / reimbursable commercial agreement
- Construction Services
USS Gary Works
Steel
Construction