
KBR LSG
The scope of work includes deconstructing and reconstructing of stick-built steel from the modules, and the disconnecting and reconnecting of structural modules to their supports. It also includes installation of the grade slab and its reinforcing and miscellaneous concrete pipe supports and electrical supports with an overall price of $68,319 MM.
Deconstruction
Material identification/tagging/inspections, Scaffolding, Isolate heavy haul modules, Electrical cable and tray removal (not reused), Fireproofing/insulation removal (subcontract), Loose steel and pipe removal, Flange breaks/pipe cutting, Heavy haul & rigging support, Removal and transport non-heavy haul items (pumps, exchangers, H2 heater, etc.).
Reconstruction (east to west)
Erect owner-furnished stick built steel, Support heavy haul module and equipment setting, Set non-heavy haul equipment (pumps, exchangers, etc.), Receive and set refurbished gas compressor & LO skid, 200’ x 300’ concrete slab, Erect loose structural steel, Reconstruct H2 heater, Reinstall all interconnecting pipe, Relocate electric panels, junction boxes and switches, Install new LED lighting, Pull and terminate 240V service cables, Perform NDE, hydro test & restore systems, Instrumentation installation & loop checks (instruments by owner), Fireproofing, insulation and painting (subcontract), System turnover.
Scope of Work
- Construction - deconstruction and reconstruction
- Installation of the grade slab and its reinforcing and miscellaneous concrete pipe supports and electrical supports
- Steel erection